Canopy - Rivets or Screws

Discussion for builders, pilots, owners, and those interested in building or owning a Sonex.

Canopy - Rivets or Screws

Postby Direct C51 » Fri Oct 07, 2016 7:43 pm

I'm installing the canopy and trying to decide if I am going to use AAP-44 rivets per the plans, or the optional AN526C-632R8 machine screws. Can anyone share what you chose to use, why you chose that method, and if you would do it any differently if you were to do it again. Thank you.
Direct C51
 
Posts: 178
Joined: Wed Jul 09, 2014 8:32 pm

Re: Canopy - Rivets or Screws

Postby Sonex1517 » Fri Oct 07, 2016 7:52 pm

Just my two cents here - I used screws to install my canopy. The reason why is if I need to remove it no drill gets near the canopy, and I was told pulling the rivets could induce stress.

Your mileage may vary.
Robbie Culver
Sonex 1517
Aero Estates (T25)
First flight 10/10/2015
325+ hours
Jabiru 3300 Gen 4
Prince P Tip
Taildragger
N1517S
User avatar
Sonex1517
 
Posts: 1651
Joined: Fri Jun 03, 2011 10:11 am
Location: Chicagoland

Re: Canopy - Rivets or Screws

Postby onex28 » Fri Oct 07, 2016 8:40 pm

Same reasons here. Takes a little more effort to tap the holes but it's worth it.

N351D flying
N951X ( reserved )
onex28
 
Posts: 219
Joined: Thu Jun 09, 2011 9:43 pm
Location: MN

Re: Canopy - Rivets or Screws

Postby Corby202 » Fri Oct 07, 2016 8:55 pm

I drilled and tapped all 3 bows and side rails, I did not countersink just used flat screws. I put heat shrink tubing on the bows first and glued the canopy on also with Sikaflex after using sikaflex primer which also looks good. My reasoning is there is no single stress point. I also put a small piece of "bungee rubber" on the safety cable so there is no sudden stop when opening. Early days yet, only 50hrs but so far so good.
Phil Bird
Sonex 759 JAB 2.2 Tailwheel
Mittagong NSW Australia
http://www.mykitlog.com/corby202/
https://www.flickr.com/photos/78427482@ ... otostream/
Corby202
 
Posts: 223
Joined: Mon Dec 30, 2013 2:08 am

Re: Canopy - Rivets or Screws

Postby mike.smith » Fri Oct 07, 2016 10:16 pm

I riveted because that's what the plans showed. I have replaced my canopy once and it was not a big deal to drill out the rivets. I don't like tapping thin wall tubing. Eventually they tend to strip. So either way works. If you rivet, use a hand puller; don't use a rivet gun. You have much more control with the hand squeezer.
Mike Smith
Sonex N439M
Scratch built, AeroVee, Dual stick, Tail dragger
http://www.mykitlog.com/mikesmith
mike.smith
 
Posts: 1409
Joined: Tue Jan 29, 2013 8:45 pm

Re: Canopy - Rivets or Screws

Postby Direct C51 » Fri Oct 07, 2016 10:30 pm

Thanks for the responses guys. Mike brought up my biggest concern with screws. Tapping the thin wall tubing and no locktite sounds like a recipe for loosening and stripped screws. Can anyone who used screws comment further on that? Thanks.
Direct C51
 
Posts: 178
Joined: Wed Jul 09, 2014 8:32 pm

Canopy - Rivets or Screws

Postby Sonex1517 » Fri Oct 07, 2016 10:51 pm

My screws have not loosened much and I check them regularly. I now have 53 hours on my Sonex.


Sent from my iPad using Tapatalk
Robbie Culver
Sonex 1517
Aero Estates (T25)
First flight 10/10/2015
325+ hours
Jabiru 3300 Gen 4
Prince P Tip
Taildragger
N1517S
User avatar
Sonex1517
 
Posts: 1651
Joined: Fri Jun 03, 2011 10:11 am
Location: Chicagoland

Re: Canopy - Rivets or Screws

Postby wlarson861 » Fri Oct 07, 2016 11:37 pm

I used screws for the same reasons as stated by others.375 hours and they have not loosened. I have had to tighten a couple on the cross bows but the lower sides have stayed put.
Bill Larson
N861SX
Sonex, polished, tail wheel, Generation 4 Jabiru 3300
wlarson861
 
Posts: 497
Joined: Wed Dec 05, 2012 11:41 pm

Re: Canopy - Rivets or Screws

Postby DCASonex » Sat Oct 08, 2016 9:15 am

First Sonex canopy cracked over first night. Todd's canopy bonded with Sika Flex, No holes. Used short sections of 1/8" wall split tubing spaced along tubular bows to give the material room to accommodate expansion, removed those after bonding between them and filled in with more Sika Flex. Modified latch to eliminate notch for that as well. Now about 310 hours on tach. No cracks has spent time at -20 F and left in hot sun.

David A. Sonex TD #1327
DCASonex
 
Posts: 904
Joined: Mon Sep 12, 2011 8:04 pm
Location: Western NY USA

Re: Canopy - Rivets or Screws

Postby pschwenn » Tue Jun 09, 2020 11:56 am

What is the best adhesive for bonding the canopy edges within the canopy aluminum side channels?

And how deeply into the steel side channels should the canopy extend (all the way to the bottom or halfway or...)? [I ask because the curved canopy (especially if the plexiglas is not more or less new and very flexible) "doesn't like" the perfectly straight channels.]

Thank you

Peter Schwenn

Xenos':
N32XS @ KCGS (912iS being installed)
N16XN under construction

6514 41st Ave
University Park MD 20782

240-602-6931
6514 41st Ave
University Park MD 20782

240-602-6931

N16XN under construction
N32SX @ KCGS (912iS being installed)
http://www.schwenn.com
Eaa4 - KCGS College Park MD
pschwenn
 
Posts: 25
Joined: Fri Jul 03, 2015 8:22 pm
Location: 6514 41st Avenue, University Park, MD 20782

Next

Return to Sonex

Who is online

Users browsing this forum: No registered users and 9 guests